Okowa On Asaba Airport: It Took 2 Yrs For ULO To Construct 900 Metres Of Runway; Setraco Have Done 1.1 Kilometre In 3 Wks
Governor Ifeanyi Okowa has expressed delight that he engaged Setraco Nigeria Limited for the reconstruction work in the Asaba Airport, saying that the fast pace of work at the re-awarded runway project shows the project would come on stream sooner than expected.
Commercial activities will be in full swing at the Asaba International Airport in July, this year when Setraco handling the new phase of the project must have deliver the job, he said.
Governor Okowa who gave this assurance after inspecting the level of work at the project site on Thursday, said that the contractor handling the reconstruction of the runway, Setraco had proven that the project could be delivered within three months.
It took ULO Consultant Limited, who recently pulled out of the project following some irreconcilable differences in the project terms two years to construct 900 metres of the runaway before his administration revoked and re-awarded the contract.
According to Okowa, “it took two years for ULO to construct 900 metres of the runway but, it gladdens my heart that in just three weeks, Setraco have done 1.1 kilometre of the runway.”
“From the work programme, it may be possible for Setraco to complete the project in three and half months, the speed with which they mobilised to site is wonderful, we thank God for intervening which made us to re-award the contract,” the Governor said.
Emphasising, he said, “we are confident that in another four months, there will be a lot of bigger planes landing here.”
Engr Jihad Yahgi, Area Manager, Setraco who explained the level done so far, disclosed that apart of the runway, the company was in the process of completing the water channels at the airport.
He assured Delta State government that work will be completed on schedule according to specifications.